Connect to Water Supply and Wastewater Disposal System
01
Apply for connection specifications
Incoming documents:
- Application for the issuance of technical specifications;
- Notarized copies of the constituent documents, as well as documents confirming the authority of the person signing the request;
- Title documents for the land plot (for the land title holder).
- The application for the issuance of connection technical specifications is registered by the resource-supplying organization (hereinafter referred to as the RSO).
02
The supplier issues the connection specifications
Incoming documents:
Connection technical specifications containing the following data:
- An application for the issuance of connection technical specifications registered by the RSO.
Connection technical specifications containing the following data:
- Maximum load at possible connection points;
- The term of connection of the capital construction facility to the engineering and technical infrastructure, determined, among other things, by the timing of the implementation of investment programs;
- The validity of the technical specifications, calculated from the date of their issuance and constituting at least 5 years providing the implementation of activities for the integrated and sustainable development of the territory, and at least 3 years in all other cases.
03
Apply for a technological connection agreement
Incoming documents:
- Application for connection;
- Copies of the constituent documents as well as the documents confirming the authority of the person signing the application;
- Notarized copies of title documents for the land plot;
- Situational plan of the facility location with reference to the territory of the settlement;
- Topographic map of the site on a scale of 1:500;
- Information on the construction (reconstruction) terms and the commissioning of the facility under construction (reconstructed);
- Balance of water consumption and drainage of the connected object during the period of the maximum power (load) use;
- Information on the composition and properties of wastewater intended for disposal in a centralized wastewater disposal system;
- Information about the purpose of the facility the height and number of floors of buildings, structures, erections;
- The urban development plan of the land plot, the results of engineering surveys or a link to the state information systems for urban planning activities where the corresponding results of engineering surveys can be found.
- A registered RSO application for the conclusion of a connection agreement (technological connection).
04
The supplier gets the connection approved by a guaranteeing organization (only required if the supplier is not a guaranteeing organization)
Incoming documents:
Resulting documents:
- An application registered by the RSO for the conclusion of a connection agreement (technological connection).
Resulting documents:
05
The supplier executes the connection agreement
Incoming documents:
Resulting documents:
- An RSO application for the conclusion of a connection agreement (technological connection).
Resulting documents:
- The draft connection (technological connection) agreement signed by the RSO with the conditions of connection (technological connection) and the connection fee (technological connection) estimation enclosed.
06
The investor executes the connection agreement
Incoming documents:
Resulting documents:
- The draft connection (technological connection) agreement signed by the RSO.
Resulting documents:
- The concluded (signed by the RSO and the investor) connection agreement (technological connection).
07
Implementation of the technological connection agreement
Incoming documents:
- Connection (technological connection) agreement registered by the RSO.
Resulting documents:
- The act of connection (technological connection) drawn up by the RSO.
08
Signing the technological connection commissioning acts
Incoming documents:
- The act of connection (technological connection) drawn up by the RSO.
Resulting documents:
- The act of connection (technological connection) signed by the RSO and the investor.
09
The investor provides initial data and documents required to engineer the connection
Incoming documents
- A plan of a well, basement (technical floor) or other room (other premises) of the projected (existing) capital construction object with an indication of the places of water service pipe, cold water metering unit, sewer outlet;
- Planned high-altitude position of the designed sewer well with the indication of the pipe bottom line to be located on the border of the applicant's land plot;
- The plan of the relief organization (vertical layout) of the land plot where the development is conducted.
- Connection (technological connection) agreement registered by the RSO